VERIFIED SOLUTION i
X

How to schedule a report to run on bank holiday in Confirm

UPDATED: August 18, 2017


How to scheduled report to run on bank holiday.
Situation is related to “Follow Up” and “Non Working Day” settings.
Scheduled Reporting Agent on the Scheduled Tasks screen it sets the Next Run Time field based on the Follow Up field.
 
 (Reporting > Reporting Lookups >Follow Ups)
 Follow Ups are set on the Follow Up screen and there is a tick box there called 'Working Days'.
We suspect that working days is ticked and Bank holiday is marked as a non-working on Non Working Day screen.
 If you wish the report to run on a bank holiday you can create a 1 week Follow Up where the Working Days checkbox is not ticked.


 
 

Environment Details

Product Feature: Task Processor

 

Downloads

  • No Downloads